Partial Building Demolition for Reconstruction into a Shopping Center
Partial demolition and dismantling works were carried out to prepare the building for its reconstruction into a shopping center. For degraded buildings (Construction Group II), above-ground and underground structures were dismantled over an area of 551.2 m².
Prior to demolition, temporary metal support frames were installed to stabilize the existing walls to be preserved, ensuring structural stability and safe working conditions. The above-ground parts of the buildings were dismantled with special care to allow the reuse of historic bricks, which were sorted and prepared for further use.
Key Works
-
Cleaning of the site and premises – 1720 m²
-
Demolition of roofs and ceilings – 1350 m²
-
Demolition of building and site structures – 400 m³
-
Collection and disposal of construction waste – 1718 m³
-
Sorting of decorative bricks for reuse – 36 839 pcs
-
Construction of temporary access roads – 300 m²
Due to the location near heavy road traffic, additional safety measures were implemented, including pedestrian traffic management, work zone fencing, and dust control.
After completion of the demolition works, the site was fully cleared and prepared for the next construction phases.